Topic:  Create a Budget for the anticipated study using the Master Budget Template spreadsheet.  See Example Budget Spreadsheet

Step 1#1:  Open the latest YYYYMMDD_Master Budget Template.xls spreadsheet, Rename and Save As StudyXXXXXX.xls.

Step 2#2:  Using the StudyXXXXXX.xls spreadsheet, modify (or) remove the number of columns, and rename the intervals(Encounters) per the study.

Step 3#3:  Use a Dark Gray Background Shade and color the rows that are not applicable at any interval in this study.

Step 4#4:  If necessary, adjust the default pricing rates where it makes universal sense .  (e.g. if a majority of the prices are different from the default rate, in any one row.)  Use a Dark Red Background Shade and color the default pricing rate cells, when a change is applied.

Step 5#5:  Begin adding pricing amounts to each cell where applicable to the budget.

Action:  Notify Study Administrator and await notification that StudyTRAX Financial Master has been updated in StudyTRAX.

Step 6#6:  Update Master Budget Template spreadsheet

...

Procedure Contact:  Study Administrator

Topic: Upon receipt of the StudyXXXXXX.xls spreadsheet, Create a new study utilizing the financial component.

Step #1:  Click on the projects main menu item at the top of the screen.  Determine if Default price rates need to be updated.

Step #2:  A new study is created as a copy of the Financial Management Master.

Step #3:  Update the pricing of each interval according to the budget.

Step #4:  After all intervals are adjusted as necessary, double check your work.  When ready, delete the "Invoicing" interval.

Step #5:  Review the Unstructured Event Encounter